A construction site can have enough generation capacity and still have an inadequate power system. The source may be rated for the combined load, but the site also needs a safe and practical way to move that power to trailers, tools, lighting, pumps, ventilation, chargers, and controls.
A temporary power distribution plan documents that path. It identifies the source, disconnects, transformers, feeders, panels or portable distribution boxes, branch circuits, cable routes, and connected loads. It also records the voltage, phase, protection, grounding and bonding arrangement, and inspection requirements for each part of the system.
The plan should be prepared and installed by qualified electrical personnel under the applicable electrical code, workplace-safety rules, permits, utility requirements, and authority having jurisdiction. This guide describes the information that project managers, superintendents, equipment suppliers, and electrical contractors can assemble before final design.

Start with a one-line path from source to load
Draw the proposed system as a one-line diagram before selecting cables or portable panels. A simple site may follow this path:
source -> main disconnect -> transformer if required -> feeder -> distribution panel -> branch circuit -> load
A larger site may have several feeders from one main distribution point, with separate panels for the office compound, active work area, lighting, pumps, and equipment charging. The drawing should show where each feeder begins and ends, its voltage and phase, and the loads served by each downstream panel.
This structure is consistent with U.S. construction requirements. OSHA 29 CFR 1926.405 states that temporary feeders originate in a distribution centre and temporary branch circuits originate in a power outlet or panelboard. The standard also requires conductor protection and addresses how temporary conductors may be installed.
The U.S. Army Corps of Engineers provides a useful example of the documentation expected on controlled projects. Its temporary-wiring guidance calls for a sketch showing circuit locations, voltages, receptacles, disconnecting means, grounding, GFCIs, lighting circuits, and protection. The exact submittal and approval requirements depend on the owner and jurisdiction, but that list is a practical starting point for any commercial site.
Gather the inputs before laying out distribution
The distribution plan follows the load plan. Assemble these inputs first:
- An equipment list with nameplate voltage, phase, frequency, current, kW or kVA, connector, and starting characteristics
- An interval load schedule showing which loads may operate together
- A site plan with the source, trailers, work areas, pumps, lighting, access roads, excavations, and future phases
- Approximate cable distance from the source to each distribution point and from each panel to its loads
- Environmental conditions, including rain, standing water, snow, dust, heat, corrosive material, and classified areas
- Vehicle routes, crane paths, material laydown areas, doorways, stairs, and other locations where cables could be damaged
- Critical loads that require backup, transfer, monitoring, or load-shedding rules
- The planned source or sources: utility, generator, battery energy storage, or a hybrid system
Do not use a general label such as "tools" or "trailer" where exact equipment data is available. Two trailers can have very different heating loads, and two pumps with the same horsepower can have different voltage, efficiency, starting current, and controls.
Our guide to jobsite power planning explains how to build the underlying load schedule and separate peak kW from daily kWh.
Confirm voltage and phase at every level
North American jobsites commonly use 120 V branch circuits for hand tools, chargers, controls, and lighting. Trailers and larger portable equipment may require 120/240 V single-phase service. Commercial and industrial equipment may use three-phase service at another voltage.
These are common arrangements, not a basis for assuming compatibility. Record the exact requirement for every load and confirm:
- Line-to-line and line-to-neutral voltage
- Single-phase or three-phase input
- Whether a neutral is required
- Frequency
- Receptacle, pin-and-sleeve, cam-lock, lug, or hardwired connection
- Grounding and bonding requirements
- Disconnect and overcurrent-protection requirements
- Whether a transformer is needed
A three-phase source does not automatically provide every single-phase voltage a site needs. A transformer changes voltage but also adds losses, inrush current, protection requirements, and a separately derived system that may change grounding and bonding details. Treat the source, transformer, panel, conductors, connectors, and loads as one coordinated system.
Divide the site into useful power zones
Place distribution points near stable groups of loads instead of running many long branch circuits from one central location. Typical zones include:
- Office and welfare compound: trailers, network equipment, HVAC, kitchen loads, and exterior lighting
- Active work floor: tool circuits, chargers, temporary lighting, and ventilation
- Water-management area: dewatering pumps, controls, alarms, and heat trace
- Site perimeter: security cameras, access control, communications, and lighting
- Equipment charging area: battery chargers, electric equipment, and managed EV charging
Zoning makes the plan easier to revise as work moves. It also allows circuits to be isolated without removing power from unrelated areas. A panel location still needs suitable access, working clearance, environmental protection, physical security, and protection from vehicles and construction activity.
Portable distribution boxes, often called spider boxes, can bring protected receptacles closer to the work. Larger distribution panels, switchgear, transformers, and transfer equipment may be required upstream. Rental suppliers such as United Rentals and Sunbelt Rentals list this equipment in many voltage, phase, and current configurations. The available connector does not establish that a device is suitable for the source, feeder, or load; the complete assembly must be selected and coordinated by qualified personnel.
Size from probable peak, then verify each circuit
The sum of all nameplate ratings is the connected load. The probable operating peak may be lower when loads follow different schedules. Prepare a 15-minute, 30-minute, or hourly schedule and identify the highest expected combination. Then check short events separately, including:
- Motor and compressor starts
- Transformer energization
- Welders and intermittent high-current tools
- Trailer heating or cooling cycles
- Battery or EV charging that begins automatically
- Simultaneous restoration after an outage
Source capacity does not replace distribution capacity. Each feeder, panel, branch circuit, connector, and protective device must be suitable for the load it serves and for the available fault current. Phase loading also needs review on three-phase systems and on 120/240 V systems with many 120 V loads.
Avoid specifying cable size from kW alone. Conductor selection depends on current, material, insulation, installation method, ambient temperature, bundling, duty, protection, terminal ratings, distance, and the governing code.
Calculate voltage drop using actual cable distance
Long temporary cable runs can deliver acceptable voltage at the source but inadequate voltage at the load. Low voltage can cause motors to start poorly, contactors to drop out, lights to dim, chargers to limit output, and electronic equipment to reset.
For every significant feeder and branch circuit, provide the electrical contractor with:
- Load current and power factor where relevant
- System voltage and phase
- One-way conductor length
- Conductor material, size, and temperature assumptions
- Expected running and starting current
- Minimum acceptable voltage at the equipment
Voltage drop is normally reported as both volts and percentage:
voltage drop percentage = voltage drop / nominal voltage x 100
For context, 3% of 120 V is 3.6 V, while 3% of 240 V is 7.2 V. A project may use a percentage target as a design check, but the applicable code, equipment limits, circuit arrangement, and total feeder-plus-branch drop must be confirmed. A percentage is not a substitute for a conductor calculation.
Measure voltage at the load under realistic demand after installation. A no-load reading will not show the drop that occurs when a pump starts or a group of tools operates.
Plan GFCI protection, grounding, and bonding together
Ground-fault protection and equipment grounding address related hazards but are not interchangeable.
In the United States, OSHA 29 CFR 1926.404 requires employers to use GFCIs or an assured equipment grounding conductor program under the conditions set out in the rule. It specifically requires approved GFCI protection for 120 V, single-phase, 15 A and 20 A receptacle outlets on construction sites that are not part of the permanent wiring and are used by employees, subject to the rule's provisions.
In British Columbia, WorkSafeBC Part 19 requires approved Class A GFCI protection for portable electrical equipment used outdoors or in wet or damp locations unless another acceptable means is provided. WorkSafeBC guidance also discusses construction and demolition receptacles and the applicable electrical authority.
Other provinces, states, owners, and project specifications may impose different or additional requirements. The electrical design should identify:
- Where the grounded conductor and equipment grounding system are bonded
- Whether a source or transformer is a separately derived system
- Equipment grounding conductors and continuity
- Grounding electrodes where required
- Neutral switching and transfer-equipment arrangement
- GFCI type, location, rating, and test procedure
- Fault-current and overcurrent-protection requirements
Do not add a neutral-to-ground bond at a downstream panel simply because the source is temporary. Multiple bonds can create objectionable current paths. The correct arrangement depends on the complete system.
Route and protect temporary cables
Cable routing changes as excavation, structure, enclosure, and interior work progress. Mark proposed routes on the site plan and inspect them regularly.
Keep temporary cables away from:
- Vehicle and equipment traffic unless an approved protection method is used
- Standing water, drainage channels, and unprotected wet areas
- Sharp edges, door pinch points, hot surfaces, and abrasive material
- Excavations and grade changes where settlement or movement can damage a cable
- Hoisting, crane, and material-handling paths
- Locations where workers could trip or where materials will be stored
OSHA's temporary-wiring provisions state that branch-circuit conductors cannot be laid on the floor and address protection from physical damage. Local rules and the installation method determine whether a cable must be elevated, supported, guarded, ramped, buried, or installed in a raceway. Use listed equipment suitable for the environment and application.
Label both ends of feeders and branch circuits. Panel schedules should use the same zone and equipment names as the one-line diagram. Where work changes frequently, a revision date on the drawing helps crews identify the current plan.
Worked example: distribution for a mixed construction site
The worked load schedule in our broader jobsite planning guide has the following peak contributions:
| Load group | Expected peak contribution | Proposed zone |
|---|---|---|
| Office and welfare trailers | 4.50 kW | Office compound panel |
| Tools and battery chargers | 6.00 kW | Active-work distribution box |
| Ventilation and air cleaning | 1.80 kW | Active-work panel, separate circuit group |
| Temporary LED lighting | 1.60 kW | Lighting panel |
| Dewatering pump | 0.75 kW running | Pump panel or local disconnect |
| Cameras, network, and controls | 0.12 kW | Critical-load circuit |
| Simple combined peak | 14.77 kW | Before starting demand |
The same example uses an estimated 83.4 kWh per day, or 100.1 kWh after a 20% planning allowance. Those energy values help select a battery and recharge plan; they do not determine feeder or branch-circuit sizes.
A preliminary one-line concept could be:
source -> main disconnect/distribution -> office feeder + active-work feeder + lighting feeder + pump feeder + critical-load feeder
The next design steps are to:
- Confirm the actual voltage, phase, current, connection, and starting data for every load.
- Place each load on an interval schedule to determine the probable peak.
- Check the pump, ventilation motors, trailer HVAC, and tool loads for starting or short-duration demand.
- Measure route length to each panel and calculate feeder and branch-circuit voltage drop.
- Select listed panels, distribution boxes, cables, connectors, protection, and disconnects.
- Define grounding, bonding, GFCI, transfer, and inspection requirements.
- Commission the system under load and record test results.
This example is intentionally not a construction drawing. It does not specify breaker ratings, conductor sizes, receptacles, fault-current ratings, or grounding details because those selections require equipment data and a jurisdiction-specific electrical design.
Distribution for battery, generator, and hybrid sources
The downstream load map may look similar for several source types, but source characteristics affect the electrical design.
Battery energy storage
Confirm continuous and short-duration inverter output, neutral and bonding configuration, fault-current behaviour, transfer operation, compatible transformers, and the voltage and phase available at the output. Battery state of charge adds an operating limit that does not exist in the same form with a utility connection.
Generator
Confirm voltage regulation, frequency response, starting performance, neutral configuration, grounding, fuel runtime, emissions, ventilation, and load-bank needs. A lightly loaded generator may operate inefficiently, while a large motor start may cause a short voltage and frequency dip.
Hybrid system
A battery-generator hybrid needs a coordinated charging and load schedule. Generator capacity must cover the active site load plus battery charging when both occur together. The controls should define start and stop thresholds, minimum run time, reserve state of charge, fault response, and manual operation.
The transfer method must prevent unintended backfeed and use equipment suitable for the source arrangement. Any connection to permanent building wiring or a utility service requires the appropriate approved interconnection and transfer equipment.
How Apex Station can fit the example
The Apex Station has published specifications of 120 kWh usable LiFePO4 capacity and 30 kW continuous output. Configurations are available for 120/240 V output and single-phase or three-phase service, with grid, generator, and solar charging compatibility.
The worked example's 14.77 kW simple combined peak is below the published 30 kW continuous rating, and its 100.1 kWh planning estimate is below the published 120 kWh usable capacity. This comparison does not establish a final system. Motor starts, inverter short-duration response, usable reserve, phase balance, transformer needs, voltage drop, distribution equipment, temperature, conversion losses, fault-current requirements, and recharge timing must all be confirmed.
The Apex Mobile provides 12 kW continuous split-phase 120/240 V output and 14.4 kWh usable battery capacity. It is not sized for the complete worked example, but it may fit an isolated tool-charging area, a lighting zone, a measured trailer circuit, or another defined subset with a regular recharge plan.
Related load calculations are available for portable tools and equipment, site office trailers, temporary lighting, construction ventilation, and dewatering pumps.
Temporary power distribution plan checklist
- Draw the source-to-load one-line diagram.
- List voltage, phase, frequency, current, kW or kVA, connector, and starting data for each load.
- Map all source, transformer, panel, distribution-box, disconnect, and load locations.
- Measure feeder and branch-circuit route lengths.
- Calculate probable peak demand and check short starting events separately.
- Verify conductor ampacity, protection, fault-current ratings, and phase balance.
- Calculate voltage drop and test voltage at the load under realistic demand.
- Define GFCI, grounding, bonding, neutral, and transfer arrangements.
- Protect cables from water, traffic, sharp edges, heat, excavation, and material handling.
- Label panels, feeders, branch circuits, disconnects, and both ends of temporary cables.
- Document inspection, continuity, polarity, GFCI, grounding, and functional tests required by the project.
- Update the plan as work zones, trades, weather, and construction phases change.
Sources
- OSHA 29 CFR 1926.404, Wiring Design and Protection
- OSHA 29 CFR 1926.405, Wiring Methods, Components, and Equipment for General Use
- WorkSafeBC OHS Regulation Part 19, Electrical Safety
- WorkSafeBC Guidelines for Part 19
- U.S. Army Corps of Engineers EM 385-1-1, Section 11, Electrical
- United Rentals, Power Distribution Equipment
- Sunbelt Rentals, Temporary Jobsite Power for Construction Sites
- Aggreko, Temporary Power Distribution Equipment