November 23, 2026

Temporary Jobsite Power Cost Calculator: Diesel, Battery, and Hybrid Systems

A generator rental rate does not show the complete cost of jobsite power. This guide provides a worksheet for comparing diesel, battery, and hybrid systems on the same project scope.

Temporary Jobsite Power Cost Calculator: Diesel, Battery, and Hybrid Systems

Temporary jobsite power should be compared on total project cost, not only the weekly rental rate. A low equipment rate can be offset by fuel deliveries, engine operating hours, service calls, electrical installation, cable, monitoring, permits, or work interruptions. A battery system can have a higher rental rate but lower daily operating cost. A hybrid system adds controls and equipment while reducing the hours a generator runs.

The calculation depends on the actual load schedule and local supplier quotes. Fuel prices, electricity tariffs, labour rates, transport distances, rental availability, and permit requirements vary across Canada and the United States. The worksheet below uses project-specific inputs so it can be updated without relying on a general cost-per-kWh claim.

Temporary power personnel measuring a generator installation area
Temporary power personnel prepare an area for a generator installation in Mississippi. U.S. Army Corps of Engineers photo by Christi Kilroy via DVIDS. Public domain.

Start with one common cost boundary

Use the same scope and operating period for every option. The comparison should begin when the equipment leaves the supplier and end when the site is restored after demobilization.

Total project cost =
  equipment rental
  + transport and lifting
  + site preparation
  + electrical installation and removal
  + distribution equipment and cable
  + fuel or charging energy
  + refuelling or charging labour
  + scheduled maintenance
  + monitoring and service support
  + permits, inspections, and environmental controls
  + expected interruption cost
  + demobilization and site restoration

Some costs are common to every option. A project may need the same panels, cable ramps, branch circuits, grounding work, and electrician time regardless of the source. Keep these costs in the worksheet, but identify them as common costs so the source comparison remains clear.

Use both of these outputs:

Project cost per operating day = total project cost / project operating days

Cost per delivered kWh = total project cost / measured load energy served

Cost per delivered kWh is useful for a site that consumes energy continuously. It is less complete for standby or mission-critical service, where the project is also paying for available capacity, response time, redundancy, and reserve.

Collect the load data before entering prices

The source has to fit the load before its cost can be compared. Record:

  • Peak running kW and kVA
  • Short-duration starting or inrush demand
  • Energy use in kWh for each shift and each 24-hour period
  • Voltage, phase, frequency, and power factor
  • Operating hours, workdays, weekends, and unattended periods
  • Loads that can be scheduled, shed, or moved to a separate source
  • Required reserve and maximum acceptable interruption
  • Expected project duration and possible extension period
  • Available grid, generator, or solar charging windows

Metered interval data is preferable to a list of nameplate ratings. If measurements are unavailable, build an interval schedule using equipment input, quantity, duty cycle, and coincident operation. The separate jobsite power load-schedule guide explains that process.

Do not use the source nameplate rating as the daily energy requirement. A 60 kW generator does not necessarily deliver 60 kW throughout the day, and a 120 kWh battery should not be planned as if every stored kilowatt-hour is available under every operating condition.

Diesel generator cost worksheet

Request the generator model, rating basis, and manufacturer fuel-consumption table at several load points. Caterpillar's published data for its XQP60 mobile generator, for example, lists different fuel consumption at 50%, 75%, and 100% load. The values also differ between 50 Hz and 60 Hz operation. This illustrates why a single litres-per-hour estimate should not be applied to every generator and load level.

For a reasonably steady load:

Daily fuel volume (L/day) = fuel burn at expected load (L/h) x engine hours per day

Daily fuel cost = daily fuel volume x delivered fuel price per litre

For a variable load, divide the day into intervals and use the appropriate fuel rate for each interval:

Daily fuel volume = sum of (fuel rate for interval x interval hours)

Include these diesel-specific inputs:

InputUnitProject value
Generator rental$/day, week, or monthEnter quote
External fuel tank and containment$Enter quote
Mobilization and demobilization$Enter quote
Fuel burn by load intervalL/h or gal/hManufacturer curve or measurement
Delivered fuel price$/L or $/galEnter supplier quote
Engine operating timeh/dayEnter schedule
Delivery charge and minimum volume$/deliveryEnter quote
Refuelling attendancelabour h/deliveryEnter schedule
Preventive maintenance$ or labour h/intervalEnter contract term
Diesel exhaust fluid, where applicablequantity and priceEnter equipment requirement
Spill controls and inspections$Enter site requirement
Noise or exhaust mitigation$Enter site requirement

Low-load operation should be visible in the calculation. Caterpillar's guidance states that standby- and prime-rated diesel generator sets are generally designed to operate between 50% and 85% of full nameplate load and describes maintenance concerns associated with extended underloading. Confirm the acceptable load range and maintenance procedure for the specific rental unit rather than applying that range to every engine.

Battery system cost worksheet

A battery stores energy supplied by the grid, a generator, or solar. Its operating-energy cost should include charging losses and any utility demand charge caused by the charger.

Charging energy (kWh) = load energy delivered / measured charging-to-load efficiency

Grid charging cost =
  charging energy x electricity energy rate
  + incremental demand charge
  + other applicable tariff charges

Use measured system efficiency where available. If a planning assumption is used, identify it and test the result at a lower efficiency. Temperature control, transformers, inverter conversion, cable losses, standby consumption, and battery conditioning can all affect the energy drawn at the charger.

Include these battery-specific inputs:

InputUnitProject value
Battery rental$/day, week, or monthEnter quote
Charger, transformer, and distribution rental$Enter quote
Mobilization and demobilization$Enter quote
Daily load energykWh/dayMeter or load schedule
Minimum operating reserve% or kWhEnter project requirement
Charging-to-load efficiency%Measurement or stated assumption
Electricity energy rate$/kWhEnter tariff or supplier quote
Incremental demand charge$/kWConfirm with utility account
Available charging powerkWVerify connection limit
Charging windowh/dayEnter schedule
Monitoring and service support$Enter contract term

Check charging power as well as charging cost. A system that needs 85 kWh from the source during a five-hour window requires an average 17 kW of charging power before accounting for the load that continues to run while charging.

Battery capacity also needs a reserve. The planned discharge should account for the required state-of-charge floor, cold or hot conditions, load growth, degradation assumptions, and an unavailable charging window. The equipment supplier should state which capacity figure is nominal and which is usable.

Hybrid system cost worksheet

A hybrid arrangement normally uses a battery to carry variable loads, overnight base load, and short peaks. A generator starts for sustained demand or to recharge the battery, then shuts down. The cost model includes both equipment sets, but generator fuel and service are based on reduced engine hours.

Hybrid daily fuel volume =
  sum of (generator fuel rate during each run interval x interval hours)

Battery energy balance =
  starting stored energy
  + energy received from grid, generator, or solar
  - site load energy
  - conversion and standby losses

The generator must be evaluated at its actual operating load while it serves the site and charges the battery. A fuel calculation based only on engine hours can be misleading if the assumed charging power is not shown.

Add these hybrid inputs to the battery and generator worksheets:

  • Generator start and stop state-of-charge thresholds
  • Minimum generator run time
  • Generator power assigned to the live load and battery charger
  • Fuel rate at the resulting load
  • Battery reserve during a failed generator start
  • Automatic-control, communications, and monitoring cost
  • Manual operating procedure if the controller is unavailable

Atlas Copco describes a hospital construction project where a battery handled low loads and the generator operated during higher demand and charging. It reports generator operating hours were reduced by up to 80% on that project. A separate POWR2 construction case study reports reducing generator runtime from continuous operation to three hours per day for an office-trailer load. These are project results, not default savings factors. A new estimate should use its own measured load, control sequence, equipment efficiency, and fuel curve.

Worked example using editable assumptions

Consider a 20-day construction project with this measured daily profile:

  • 6.5 kW average for a 10-hour work shift: 65 kWh
  • 0.8 kW average for the remaining 14 hours: 11.2 kWh
  • 76.2 kWh total load energy per day
  • 18 kW measured running peak
  • Starting demand already verified separately

The following energy inputs are illustrative. They are not current market prices or supplier quotes.

AssumptionDiesel-onlyBattery-onlyHybrid
Generator operation24 h/dayNone4 h/day
Generator fuel burn during operation3.2 L/hNone8.0 L/h while serving load and charging
Delivered diesel input$1.80/LNone$1.80/L
Charging-to-load efficiencyNot used90%Included in the stated hybrid operating profile
Grid electricity inputNot used$0.16/kWhNot used in this example

The variable-energy calculation is:

CalculationResult per dayResult for 20 days
Diesel: 3.2 L/h x 24 h x $1.80/L$138.24$2,764.80
Battery: (76.2 kWh / 0.90) x $0.16/kWh$13.55$271.00
Hybrid: 8.0 L/h x 4 h x $1.80/L$57.60$1,152.00

This table compares only fuel or grid energy under the stated assumptions. It does not establish the lowest total project cost. Add the rental, transport, installation, distribution, charging connection, service, labour, permits, and demobilization quotes for each option.

The example also shows why litres per hour cannot be compared without engine hours. The hybrid generator has a higher fuel rate while running because it carries the live load and charges the battery, but it runs for fewer hours.

Calculate the break-even project length

If the battery or hybrid option has a higher installed fixed cost, calculate how long its daily operating savings take to recover that difference.

Break-even operating days =
  additional fixed cost / daily operating-cost reduction

Using the illustrative diesel and battery energy costs above, the daily difference is $124.69. If the battery option's combined rental, transport, installation, and charging connection were $4,000 more than the diesel option, the simple break-even period would be about 32 operating days.

That calculation should be tested against changes in fuel price, efficiency, work schedule, project extension, and charging availability. It should also include any additional utility demand charge and any diesel delivery minimum.

Include labour, logistics, and interruption costs

Energy is only one part of temporary jobsite power. Compare the operating tasks created by each option:

  • Fuel ordering, delivery coordination, escorts, and refuelling
  • Charger connection, charging windows, and state-of-charge monitoring
  • Scheduled engine service and maintenance shutdowns
  • Battery, generator, and controller alarms
  • After-hours callouts
  • Snow clearing, access, security, and equipment inspections
  • Spill prevention and response
  • Noise barriers, long cable runs, or restricted operating hours
  • Replacement equipment and service response time

For a load that can stop work, keep expected interruption cost as a separate line:

Expected interruption cost =
  estimated probability of an interruption x estimated cost per interruption

The estimate can include idle labour, equipment standby, restart time, spoiled materials, missed production, or schedule penalties. The assumptions should be documented; do not use a precise dollar value when the probability and consequence are unknown.

For critical work, the lowest expected cost may include redundant capacity, a reserve source, or a service contract. The temporary power contractor scope checklist covers response, commissioning, monitoring, and replacement-equipment terms.

Where Apex Station can fit

The Apex Station has published specifications of 120 kWh usable LiFePO4 capacity, 30 kW continuous output, and 60 kVA or greater peak output capacity. It is available in 120/240 V and single-phase or three-phase configurations and can charge from grid, generator, or solar.

The worked example's 76.2 kWh daily load and 18 kW running peak are below the published usable capacity and continuous output. That is an initial energy-and-power screen, not a completed design. The final assessment still has to confirm:

  • Required reserve and usable state-of-charge range
  • Motor, transformer, and tool starting demand
  • Voltage, phase, frequency, grounding, and protection
  • Conversion, standby, cable, and transformer losses
  • Charging source, input limit, charging time, and continued load during charging
  • Temperature, ventilation, placement, and access
  • Project extension and missed-charge scenarios
  • Temporary distribution and inspection requirements

For a hybrid comparison, Apex Station can carry overnight and variable loads while a generator is scheduled for charging and sustained high demand. Use the actual charger input, generator fuel curve, control thresholds, and measured load schedule in the cost worksheet.

The general technology differences are covered in electric generators versus diesel generators. The temporary power distribution guide covers panels, feeders, protection, grounding, voltage drop, and cable routing that may be common to all three source options.

Procurement checklist

  • Issue one measured load profile and project schedule to every bidder.
  • Require peak kW or kVA, daily kWh, starting demand, voltage, and phase to be addressed separately.
  • Request the proposed generator model and its load-specific fuel curve.
  • Ask for nominal and usable battery capacity, operating reserve, efficiency, and charging limit.
  • Require the hybrid control sequence and expected generator load while charging.
  • Separate rental, transport, installation, distribution, energy, labour, maintenance, monitoring, and demobilization.
  • Use delivered fuel prices and the applicable electricity tariff.
  • Include minimum fuel deliveries, utility demand charges, overtime, extension rates, and service calls.
  • Record every planning assumption and test a higher-load or longer-project case.
  • Compare total project cost, cost per operating day, and cost per delivered kWh.
  • Confirm the design with qualified electrical personnel and the applicable authority before installation.