Energy infrastructure projects often need temporary power months before permanent station service or a grid connection is available. The requirement can begin with survey equipment and a small field office, expand to pumps, tools, welding, lighting, and material handling, then change again when testing and commissioning begin.
This pattern applies to transmission lines, substations, pipeline facilities, solar and wind projects, battery energy storage sites, utility-scale generation, and other remote civil works. The permanent asset may eventually transfer large amounts of energy, but the construction site still needs a separate plan for ordinary low-voltage loads.
A useful plan starts with the work schedule rather than a single generator rating. It separates peak power, daily energy, voltage and phase, temporary distribution, recharge access, critical loads, and the sequence for moving from temporary to permanent service.
Why these projects need a different load plan
Energy infrastructure work has several characteristics that complicate temporary power:
- The project may be far from a utility connection or public road.
- Work zones can be spread along a transmission or pipeline corridor.
- Loads change substantially between civil work, equipment installation, and commissioning.
- Some activities occur during tightly controlled outage windows.
- Existing high-voltage equipment may remain energized near the work area.
- Pumps, heaters, controls, communications, and security may need to run after the crew leaves.
- Large intermittent equipment can have a high peak demand but a low average load.
- Environmental permits, noise limits, fire plans, and fuel-storage rules can affect equipment placement and operation.
The U.S. Department of Energy describes temporary power being used for both construction and testing during a substation project at Idaho National Laboratory. Competitor project coverage also shows hybrid battery-generator systems supporting major infrastructure compounds and high-demand construction equipment. These examples point to the same planning need: the source must follow the project phase and load profile rather than remain fixed from mobilization through commissioning.

Divide the project into power phases
One temporary system may not be the best fit for every stage. Prepare a load schedule for each major phase.
Mobilization and site establishment
Early loads are often modest but continuous:
- Office and welfare trailers
- Internet, radios, network equipment, and satellite terminals
- Cameras, access control, and security lighting
- Surveying equipment and battery charging
- Small tools and temporary receptacles
- Environmental monitoring and weather stations
- Frost protection, heat trace, or limited space conditioning
This phase can suit battery-only operation when daily energy is known and charging is available. A small generator-battery hybrid can also avoid operating an engine continuously for a low overnight base load.
Civil work and foundations
Earthwork and foundation activity adds larger and less predictable loads:
- Dewatering and sump pumps
- Concrete tools, vibrators, and curing equipment
- Cut-off saws, drills, grinders, and tool chargers
- Ventilation or air cleaning in enclosed work areas
- Temporary lighting for early, late, or overnight work
- Compressors and hydraulic power units
- Laydown-yard and material-handling support equipment
Motor starting and cycling become important in this phase. A pump with a moderate running load can create a much larger short starting demand. The power source, cables, transformer, and protection must all tolerate the start without excessive voltage drop.
Structural and equipment installation
As steel, electrical equipment, process piping, or renewable-energy components arrive, the site may add:
- Welders and welding ventilation
- Cable pullers and tensioners
- Torque tools and hydraulic pumps
- Hoists, winches, lifts, and small cranes
- Equipment heaters and enclosure conditioning
- Transformer oil-processing or vacuum equipment
- Larger construction trailers and additional trade compounds
Some of these loads are too large or too variable for a smaller mobile battery system. They can be placed on a separate generator or larger temporary service while a battery supports the steady base load. Separating circuits prevents one short high-demand task from determining how every other site load is powered.
Testing and commissioning
Commissioning can reduce ordinary construction activity while introducing electrically sensitive or operationally critical loads:
- Protection, control, automation, and communications panels
- Test sets and temporary instrumentation
- Battery chargers and DC control-power systems
- HVAC, enclosure heaters, and dehumidification
- Transformer oil pumps, filtration, and processing equipment
- Temporary lighting and monitored access
- Computers, data acquisition, and remote engineering support
High-voltage and high-power testing needs its own work controls. OSHA 1926.963 requires protective work practices at temporary and permanent test areas and calls for temporary wiring and connections to be protected against damage and accidental interruption. It also addresses separation of signal, control, ground, and power cables where possible.
The temporary source should have stable voltage and frequency that are compatible with the test equipment. Grounding, bonding, neutral treatment, isolation, power quality, and transfer methods require review by the project's electrical and commissioning teams.
Build a separate load schedule for each work zone
Long or distributed projects are easier to plan by zone. A substation project might use separate schedules for the office compound, civil work area, control building, switchyard, and laydown yard. A transmission project may have several active structure sites, a conductor-stringing location, and a central compound.
For each load, record:
- Equipment description and exact model
- Quantity
- Rated watts, kilowatts, amps, or kVA
- Voltage, phase, frequency, and power factor
- Running and starting current
- Operating hours and duty cycle
- Earliest start and latest stop time
- Required receptacle or connection method
- Distance from the proposed source
- Critical, deferrable, or non-critical status
- Project phase and expected removal date
Use nameplates and manufacturer documentation where available. Horsepower describes mechanical output, not electrical input. Amps alone are also insufficient unless voltage, phase, and power factor are known.
The general jobsite power-planning guide explains the kW, kVA, motor-start, and interval-scheduling calculations in more detail.
Worked example: remote substation work zone
The following example represents a defined work zone during civil and early equipment installation. It excludes large welders, cranes, transformer oil-processing equipment, and other major loads that would be scheduled separately. Actual projects should replace every assumption with equipment data or measurements.
| Load | Average input while operating | Operating time | Daily energy | Peak contribution |
|---|---|---|---|---|
| Office, network, and document station | 0.60 kW | 24 hours | 14.4 kWh | 1.80 kW |
| Tool and instrument charging | 1.50 kW | 8 hours | 12.0 kWh | 3.00 kW |
| Temporary LED lighting | 1.20 kW | 12 hours | 14.4 kWh | 1.20 kW |
| Dewatering pump | 1.50 kW | 6 hours | 9.0 kWh | 1.50 kW running |
| Small tools and intermittent equipment | 2.00 kW | 4 hours total | 8.0 kWh | 4.00 kW |
| Cameras, access control, and environmental monitoring | 0.15 kW | 24 hours | 3.6 kWh | 0.15 kW |
| Test equipment and temporary controls | 1.00 kW | 4 hours | 4.0 kWh | 1.50 kW |
| Calculated total | 65.4 kWh | 13.15 kW before motor starting |
Adding a 20% planning allowance gives:
65.4 kWh x 1.20 = 78.5 kWh
The allowance can cover conversion losses, reserve, temperature, cable losses, schedule variation, and estimation error. The required margin is project-specific. It does not replace standby capacity for loads that cannot be interrupted.
The simple 13.15 kW peak assumes every listed peak contribution occurs together. An interval schedule may show a lower probable operating peak, but the system must still be checked against pump starting, charger inrush, and sudden tool loads.
Keep major intermittent loads separate
The worked example remains within a moderate power range because it excludes high-demand equipment. That separation is useful on energy infrastructure projects.
For example, one large welder, compressor, oil-processing skid, or electric heater can exceed the combined daily loads of the office, lighting, security, and communications systems. Connecting it to the same source may require:
- A much larger inverter or generator
- Higher-voltage or three-phase distribution
- Larger feeder cables and overcurrent protection
- A transformer
- Additional battery storage or generator fuel
- A different grounding and bonding arrangement
A practical layout may use one source for the 24-hour base load and separate equipment for scheduled high-demand work. The battery then remains available for communications, lighting, monitoring, pumps, and controls when the high-demand source is shut down.
Plan distribution across distance
Source capacity is only one part of the design. Remote work zones can be hundreds of metres from the nearest practical equipment location.
The distribution plan should address:
- Feeder and branch-circuit ampacity
- Voltage drop at normal load and during motor starts
- Overcurrent and ground-fault protection
- Grounding, bonding, and neutral configuration
- Transformers and voltage conversion
- Wet, dusty, corrosive, or classified locations
- Road crossings, tracked equipment, excavations, and sharp edges
- Cable ramps, trenching, elevation, or other physical protection
- Disconnects, lockout, transfer, and emergency shutdown
- Inspection, testing, labeling, and access control
OSHA 1926.405 states that temporary feeders originate at a distribution centre and branch circuits originate at a power outlet or panelboard. It also requires conductors and temporary wiring to be protected according to the construction rules. OSHA 1926.404 addresses ground-fault protection, grounding, bonding, and generator-derived systems.
In British Columbia, WorkSafeBC's electrical guidance covers Class A GFCI protection for portable electrical equipment used outdoors or in wet or damp locations and discusses construction-site receptacles. Requirements vary across Canadian provinces, U.S. states, utilities, owners, and local authorities. A qualified electrical contractor should design, install, test, and inspect the temporary system.
Work safely near existing energy systems
Temporary-power equipment does not reduce the controls required around energized infrastructure. The work plan should identify existing overhead, underground, and concealed circuits before equipment, tools, cranes, or temporary wiring are placed.
OSHA 1926.416 requires the employer to determine whether exposed or concealed energized circuits are positioned so that people, tools, or machines could contact them. Utility owner requirements, minimum approach distances, switching orders, grounding procedures, permits, and lockout controls still apply.
Other placement considerations include:
- Fire separation and access for emergency response
- Generator exhaust and prevailing wind
- Fuel storage and spill containment
- Battery-system clearances and manufacturer instructions
- Flooding, snow, dust, wildfire, and extreme temperature
- Security and protection from unauthorized operation
- Cable routing that does not cross step- and touch-potential control zones without review
The project's electrical safety plan should govern temporary equipment near a substation, line, generation facility, pipeline station, or operating energy-storage site.
Choose battery-only, generator, or hybrid operation
Battery-only
Battery-only operation fits a defined load with enough stored energy and a reliable recharge window. It can be useful for offices, communications, security, lighting, test equipment, controls, and smaller tools. It also avoids local engine exhaust and reduces operating noise while discharging.
Daily energy and continuous output both need to be checked. A battery may have enough kWh for a day but lack the output, voltage, phase, or motor-start capability for one required load.
Generator-only
A generator can serve sustained high loads and remote projects with established fuel logistics. It may be the direct choice for large welders, compressors, heaters, or commissioning skids.
Generator sizing should not be based only on the largest possible connected load. Extended operation at a low fraction of rated output can be inefficient, while motor starts and load steps may require additional capacity. Fuel delivery, refuelling intervals, noise, exhaust, maintenance, and standby arrangements should be included in the plan.
Battery and generator hybrid
A hybrid system can use a battery for the steady low load, short peaks, and overnight operation. The generator can start during planned charging or sustained high-demand periods.
Aggreko and Atlas Copco describe construction hybrid systems in which battery storage reduces generator running hours and supports varying or peak loads. These are supplier examples rather than universal savings estimates. Actual performance depends on the measured load profile, control settings, generator size, battery capacity, charging power, project duration, temperature, and fuel logistics.
The hybrid control plan should define:
- Generator start and stop state of charge
- Maximum battery charge power
- Simultaneous load and charging limits
- Minimum generator run time
- Peak-shaving and load-shed priorities
- Response to a failed source, charger, or controller
- Manual operation and emergency bypass
The guide to electric generators versus diesel generators compares these operating characteristics in more detail.
Confirm recharge capacity
The worked example uses 65.4 kWh per day before allowance. Restoring that energy in an eight-hour charging window requires at least:
65.4 kWh / 8 hours = 8.2 kW average charging power
Charging losses increase the required input. If the site remains live during charging, the utility service or generator must also carry the active load. A 10 kW supply is not enough to charge at 8.2 kW while the work zone simultaneously draws 6 kW.
Solar can contribute where the site has suitable space and exposure, but production varies with weather, season, shading, snow, and array orientation. Use a conservative measured or modelled daily contribution rather than assuming the array will restore the battery every day.
Define critical loads and contingency response
Energy infrastructure projects can have loads that cannot simply stop when a source trips. Classify them before construction starts.
Possible critical loads include:
- Dewatering or flood-control pumps
- Freeze protection and heat trace
- Fire, gas, environmental, and security monitoring
- Communications required for switching or coordinated work
- Test equipment during a controlled procedure
- Control-power systems during commissioning
- Required lighting, ventilation, or access control
The contingency plan should state which circuits transfer to a standby source, how alarms are delivered, who responds after hours, how long stored energy must last, and which non-critical loads are shed first. For an outage window, test the transfer and backup sequence before the permanent system is taken out of service.
Where Apex Station and Apex Mobile fit
The Apex Station has 120 kWh of LiFePO4 storage and 30 kW continuous output. Published configurations include 120/240 V output, single-phase and three-phase arrangements, and grid, generator, or solar charging compatibility.
The worked example's 78.5 kWh planning requirement is below the published 120 kWh nominal storage capacity, and its 13.15 kW simple combined peak is below the 30 kW continuous rating. This comparison does not confirm a final system. Usable reserve, temperature, phase balance, voltage, pump starting, cable losses, charger demand, connection method, redundancy, and other work zones must be verified.
Large welders, compressors, oil-processing equipment, electric heaters, and some three-phase commissioning loads may exceed the Apex Station's output or voltage configuration. Those loads may need a separate source, transformer, or a coordinated hybrid arrangement.
The Apex Mobile provides 16 kWh nominal capacity, 14.4 kWh usable capacity, and 12 kW continuous output. It can fit a smaller office, communications package, monitoring system, test station, lighting zone, or tool-charging area when the exact voltage and runtime are compatible. It is not sized for the complete 78.5 kWh example without repeated charging or substantial load reduction.
Final planning checklist
Before mobilization:
- Divide the project into construction and commissioning phases.
- List loads by work zone and record exact electrical data.
- Calculate daily kWh, simultaneous kW or kVA, and motor starts.
- Separate major intermittent loads from the continuous base load.
- Confirm voltage, phase, grounding, bonding, and temporary distribution.
- Check cable distance, voltage drop, environmental exposure, and physical protection.
- Establish charging, fuel, and maintenance schedules.
- Identify critical circuits and load-shed priorities.
- Test standby, transfer, alarm, and manual-control procedures.
- Update the load schedule whenever the project phase or trade mix changes.
Temporary power for energy infrastructure projects is most reliable when it is treated as a changing site system rather than a single piece of equipment. A phase-based load schedule gives the project team a practical basis for selecting battery storage, generators, distribution, recharge capacity, and backup arrangements.