Temporary power for a festival food court starts with two separate questions: what connection does each vendor need, and how much power will all vendors use at the same time? A coffee stand that draws heavily during service and a refrigerated trailer that runs through the night may need very different arrangements, even if both ask for the same outlet.
Rental providers such as United Rentals and Aggreko include food service in broader event power and distribution planning. This guide focuses on the vendor row. For stages, lighting, and other event zones, see the outdoor event power planning guide.

Ask each vendor for an equipment schedule
Collect this information before assigning booth locations or confirming electrical service:
- Connection: Voltage, phase, inlet or plug type, and amperage requested. For a truck with a shore-power inlet, ask for the truck's inlet specification and equipment list.
- Appliances: Nameplate photos for refrigerators, freezers, warmers, espresso machines, griddles, water heaters, exhaust fans, and other electrical equipment. Note any dedicated circuits required by the manufacturer.
- Operating hours: Setup, preheating, public service, cleanup, overnight refrigeration, and the next day's restart.
- Simultaneous use: Which appliances can run together, especially before opening and during the busiest meal period?
- Continuity: Which loads must stay on if other circuits are shut down? Who monitors refrigeration temperatures and responds if power is lost?
Event forms show why these details vary. Kaslo Jazz Etc Festival in BC lists an included 20 A duplex receptacle and offers additional power. The North Carolina Folk Festival lists a base 120 V, 20 A circuit and asks vendors to declare additional requirements. Neither is a universal entitlement. Confirm the venue's allocation and whether a duplex receptacle is on one circuit or on separate circuits.
Keep circuit capacity separate from estimated energy
A 120 V, 20 A circuit has a nominal rating of 2.4 kVA, calculated as voltage times current. That is not a promise of 2.4 kW of continuous usable power. The contractor must check allowable circuit loading and appliance requirements. For equipment with a power factor below one, apparent power in kVA also differs from real power in kW. A refrigerator compressor may draw more current at startup than its running wattage suggests.
For peak demand, list the appliances that can be on at the same time. Check source capacity and each circuit or phase separately; a total below the source rating will not prevent an overloaded branch circuit. For energy, multiply average real power by operating hours for each load. Use measured consumption where possible, particularly for thermostatically controlled equipment. A warmer drawing 1.5 kW when energized uses 4.5 kWh over three equivalent hours at full draw, not necessarily 1.5 kW times every hour it is plugged in.
Worked example: four booths at a one-day festival
These are illustrative inputs, not appliance specifications. The example covers four booths with refrigeration and checkout equipment, two of which also use warmers and one of which also uses a coffee brewer.
| Load | Assumed operation | Daily energy |
|---|---|---|
| Four refrigerators | 0.25 kW average each for 12 hours, including setup and cleanup | 12 kWh |
| Four checkout and lighting sets | 0.05 kW each for 10 hours | 2 kWh |
| Two food warmers | 1.5 kW each for three equivalent full-load hours | 9 kWh |
| One coffee brewer | 1.5 kW for four equivalent full-load hours | 6 kWh |
| Total | Before system losses or reserve | 29 kWh |
If each refrigerator draws 0.5 kW while running and all listed equipment is on, the coincident running load is 6.7 kW before compressor starts. Check both the busiest service period and pre-opening heat-up. If the four refrigerators remain on for another 12 hours at the same average draw, add 12 kWh. The full-day requirement then becomes 41 kWh before losses and reserve. Overnight demand may differ with ambient temperature and door use, so verify it rather than treating the example as a forecast.
An additional 3 kW cooking appliance would add 3 kW to coincident demand if it ran during the same peak. Two equivalent full-load hours would add 6 kWh. Review substitutions with the power contractor before approving them; the issue may be the assigned circuit rather than the source's overall capacity.
Agree on overnight power and the recharge window
Assign refrigeration circuits separately from discretionary cooking loads where the electrical design permits. Agree on which circuits stay energized after close, who checks them, and where perishable stock goes if the planned supply is unavailable. Have the event's food safety lead verify the required cold-holding plan with the local health authority.
For multiday battery operation, check the energy needed between charging opportunities, not just during public hours. If loads remain active while charging, verify that the available input supports both the proposed recharge rate and those loads under the actual system configuration. Ask for a fallback if a charge window is missed.
Have a qualified temporary electrical contractor verify supply, grounding and protection, distribution, wet-weather suitability, public cable crossings, inspections, and permits. Requirements vary by location: compare the City of Surrey's temporary-event electrical permit guidance with Redmond, Washington's event electrical scope for examples of local requirements and responsibilities.
When to evaluate Apex Station
The Apex Station is rated at 30 kW continuous output and 120 kWh usable battery capacity, with grid, generator, and solar charging compatibility. The example's 6.7 kW running load and 41 kWh full-day demand are below those published ratings. That is a preliminary screen for this vendor group, not a runtime guarantee or an electrical design. Confirm the actual voltage and phase configuration, phase loading, appliance starts, distribution, reserve, and recharge schedule. Large electric cooking loads or a second vendor row can change the result substantially.
When comparing venue power, a battery, or a hybrid setup, send each supplier the same equipment schedule and operating hours. Ask for separate prices for the source, vendor distribution, delivery, and operating support. The temporary power cost worksheet gives a structure for comparing those quotes.